New Gym build Album
This new gymnasium was started in May 2012 with Maycroft ConstructionRector Gerard Tully
Turning the first sod for the new gym build on 11 May 2013
Blessing of proposed gym site
Fr Barry O'Connor SM
The blank canvas
The site was prepared and base course laid
laying of foundations
The drainage was completed 23 June 2013
Foundations
The pour of the foundations 25 July 2013
Poured gym floor
Half completed gym floor, 700sq m of the the total 1800sq m with 90cu m of concrete. 16 August 2013
first wall being prepared.
This boxing was erected 16 September 2013
the first poured wall slab is completed
24 September 2013
Level two of gym wall being prepared for pouring. 7 October 2013
The placing of wall panels at the Northern end of the gym 15 October 2013
Jonothan Moss (1988-92) Project Manager 29 October 2013
Construction of the steel work 5 November 2013
final pour of the changing rooms floor 8 November 2013
The positioning of the second level of the 13m wall panels on the western side of the gym 11 November 2013
The upper level weight training floor prep 11 December 2013
The steel work of the foyer
The roof being laid
18 December 2013
10 January 2014
28 January 2014
Near structure is storage and Gym PE offices on ground floor and upper floor Sports Director office and storage. Far structure is entrance and foyer 10 February 2014
Body of gym 14 Feb 2014
gym classroom 14 Feb 2014
weight training room 14 Feb 2014
Note low windows on southern wall 10 March 2014
Wooden floor about to be laid 4 April 2014
The Sports directors office and store room 4 April 2014
The weight training room 4 April 2014