New Gym build Album

This new gymnasium was started in May 2012 with Maycroft Construction

Rector Gerard Tully

Rector Gerard Tully
Turning the first sod for the new gym build on 11 May 2013

Blessing of proposed gym site

Blessing of proposed gym site
Fr Barry O'Connor SM

The blank canvas

The blank canvas
The site was prepared and base course laid

laying of foundations

laying of foundations
The drainage was completed 23 June 2013

Foundations

Foundations
The pour of the foundations 25 July 2013

Poured gym floor

Poured gym floor
Half completed gym floor, 700sq m of the the total 1800sq m with 90cu m of concrete. 16 August 2013

first wall being prepared.

first wall being prepared.
This boxing was erected 16 September 2013

the first poured wall slab is completed

the first poured wall slab is completed
24 September 2013

Level two of gym wall being prepared for pouring. 7 October 2013

The placing of wall panels at the Northern end of the gym 15 October 2013

Jonothan Moss (1988-92) Project Manager 29 October 2013

Construction of the steel work 5 November 2013

final pour of the changing rooms floor 8 November 2013

The positioning of the second level of the 13m wall panels on the western side of the gym 11 November 2013

The upper level weight training floor prep 11 December 2013

The steel work of the foyer

The roof being laid

18 December 2013

10 January 2014

28 January 2014

Near structure is storage and Gym PE offices on ground floor and upper floor Sports Director office and storage. Far structure is entrance and foyer 10 February 2014

Body of gym 14 Feb 2014

gym classroom 14 Feb 2014

weight training room 14 Feb 2014

Note low windows on southern wall 10 March 2014

Wooden floor about to be laid 4 April 2014

The Sports directors office and store room 4 April 2014

The weight training room 4 April 2014


<< Back to Galleries List